The off-site baseline monitoring results of the
Eco-co-combustion pilot plant are now available.
Please click here for details.
Waste-to-Energy:
Eco-co-combustion of
Municipal Solid Waste With Cement Production
By Green Island International (BVI) Ltd.
In collaboration with
The
Hong Kong University of Science and Technology
Funded by
Innovation and Technology Fund
under the University-Industry Collaboration Programme
Background: Waste Management In Hong Kong
- Increasing amount of waste generation, on average 3%
growth per year over the past few years. In 2006, 9,279 tonnes
per day (tpd)
of municipal solid waste was disposed at landfills
(Source:
Monitoring of Solid Waste
in Hong Kong 2006, Environmental Protection Department), which
is equivalent (in volume) to about 100 double-deck buses.
- Space of the three strategic landfills will be exhausted
in 5 to 8 years.
- Recycling solves only part of the waste problems, end-solution
for the non-recyclables/ non-recoverables is needed. The mission
of HK
Environmental Protection Department (EPD) is to move
from the strategy of waste disposal (i.e. landfills) to
waste
minimization and recovery pertaining to both the material and energy
content.
Project Rationale: Waste-to-Resources Recovery
The
project aims at developing the process and equipment design
for an integrated waste management system. Its uniqueness is
a synergy with cement manufacturing, utilizing its flue gas neutralizing
capability to conduct thermal treatment of non-recyclable fraction
of waste in a sustainable, safe, and pollution-free way.
Two advantages of the Waste-to-Resources recovery
strategy:
- Waste-to-Materials Recovery
Reuse of residual ash resulted from the treatment process
as clinker input for cement manufacturing.
- Waste-to-Energy Recovery
Recovery of energy generated from exothermic destruction
of waste as an alternative energy input for cement
manufacturing, thereby reducing consumption of
non-renewable fossil fuels (e.g. coal).
Integrated Waste Management System
Unlike the conventional incinerator characterized by
mass burning as well as conventional practice of waste
management, Eco-co-combustion aligned with a material recovery
and recycling facility at the front-end to separate out the
recyclables from the input waste. This ensures that
the waste with recycling value can be sorted out before
final treatment by Eco-co-combustion.
The following picture compares the life cycle of waste under the
scenarios of landfill and Eco-co-combustion.
The Pilot Plant Study - Introduction
- The study involved a demonstration facility to be built within GIC in Tap Shek Kok,
Tuen Mun, consisting of a material recovery and recycling facility and a
Eco-co-combustion facility for thermal treatment of waste.
- As required by Section 14 of the Air Pollution Control Ordinance, GIC
submitted its license application to the Environmental Protection Department (EPD)
on 30 October 2002. EPD granted the license on 25 November 2003, allowing the
operation of the pilot plant in Tap Shek Kok.
EPD’s website contains the details regarding the license.
The Pilot Plant Study – FAQ's
- How long will be the operation of the Pilot Plant?
According to EPD's license conditions, the Pilot
Plant can only be operated for a cumulative duration of 16
weeks maximum over the licensing period of two years
(effective from 25 November 2003). This involves a number of
testing modes, plant shutdown and adjustments will take place between
different modes. So, the
duration of the Pilot Plant operation is calculated
in terms of the cumulative days of actual operation.
- What will be the scale of the Pilot Plant?
According to EPD's license conditions, the
Pilot Plant can treat not more than 24 tonnes of
municipal solid waste per day. This is a small
scale compared to Hong Kong’s daily disposal of more than 9,000 tonnes
of municipal solid waste.
- How to monitor the environmental performance of the
Pilot Plant?
During the Pilot Plant operation, independent
monitoring on emission performance will be employed. The Hong Kong
Productivity Council is the Independent Consultant ("the
Independent Consultant") and is
responsible for the monitoring of the ambient air quality in
terms of total suspended particulates, respirable suspended
particulates, sulphur dioxide, nitrogen dioxide, heavy metals
and dioxins. The Independent Consultant will also monitor the
on-site emission of particulate matter, heavy metals and
dioxins. According to the EPD's license conditions, the
data of the on-site and continuous parameters have to
be made continuously and instantly available to EPD
for its surveillance. The Independent Consultant
is using the laboratory
of the Hong Kong Baptist University for sample analysis.
- Any adverse impacts on human health?
EPD's license requires the Pilot Plant to fully
comply with the emission limits which are in line with the
most stringent international standards, including heavy metals
and dioxins.
- Will the Pilot Plant stand forever?
The Pilot Plant is a temporary facility for
verification purpose only. The key objective is to collect the data for further evaluation of the
technical feasibility of the Eco-co-combustion process.
The Pilot Plant Study
- Construction & Commissioning
The plant
was installed by February 2005, and was
commissioned in April and July/August 2005 in order to demonstrate its
performance to EPD according to the licensing conditions.
Continuous operation of the pilot plant was started in early October 2005
and completed in December 2005. No more than 24 tonnes of municipal solid waste was treated every
day for a cumulative period of 11 weeks.
Two
off-site stations had been established in
Butterfly Estate and Lung Kwu Tan Village for baseline
monitoring of ambient air quality. The monitoring
had commenced in December 2004 and was
continued throughout the pilot plant study until one month after
the project finished.
The off-site baseline monitoring results are now available. Please click
here.
Subsequent to the successful load commissioning trials, the
Environmental Protection Department had agreed to the use of the
pilot plant for a limited period during which the company
analysed recovery and recycling as well as the disposal of
non-recyclable materials. The operating scale, including both
duration and volume of waste being handled remained the same
as originally planned.
As the original Specified Process (SP) license expired before
the completion of the pilot project, an application for renewal
of the license was submitted to the
Environmental Protection Department so as to complete the plant
testing of the technology. There was no increase in either
the 16-week cumulative operating time of the pilot plant or the volume of
waste being handled (not more than 24 tonnes per day).
Note: The SP license was renewed effective from 25th
November 2005 and expired on the 24th November 2007
under the same terms and conditions of operation as before. As
the project is completed, there will be no further renewal.
The pilot plant project has completed its research objective and the pilot
plant operation was closed down on 17th
December 2005.
- Decommissioning of the Pilot
Plant
The decommissioning of the pilot plant is a Designated Project
(DP) as it is included in the category of projects which
requires an Environmental Permit (EP) for decommissioning under
the Environmental Impact Assessment Ordinance (EIAO Cap.499).
The decommissioning process for the pilot plant was started with
the preparation and submission of a Project Profile (PP) to the
Environmental Protection Department (EPD) in accordance with the
guidelines under the EIAO. Following review and public
consultation on the PP, the EPD has issued an Environmental
Impact Assessment Study Brief (EIA-SB). An EIA report conforming
to the requirements of the EIA-SB was prepared for submission to
EPD to obtain an EP for decommissioning of the pilot plant.
As part of the EP application process, a Contamination
Assessment Plan (CAP) has to be approved by the EPD.
Accordingly, a CAP was prepared and submitted to EPD for review
and comments. The CAP was approved by the EPD on 29 January 2008
and Site Investigation (SI) work was carried out in compliance
with the regulatory requirements.
After completion of the SI work, a Contamination Assessment
Report (CAR) was compiled and presented to EPD and approval was
received on 27 May 2008.
A demolition permit from the Buildings Department (BD) is also
required for the decommissioning of the pilot plant. A
Demolition Plan was prepared in co-operation with the building
consultant and an application for approval of the Demolition
Plan was submitted to the BD on 20 January 2009. The Demolition
Plan was approved by the BD on 13 March 2009.
Work was continued on the EIA in co-operation with the
environmental consultant and after a series of studies and
evaluation the EIA report was submitted to the EPD on 20 March
2009. Following further amendments as required by the EPD and
consultation, advice was received from the EPD on 4 May 2009
that the EIA report is suitable for public inspection. The EIA
report was made available for public inspection from 15 May 2009
to 13 June 2009.
After the public inspection period, the EIA report for the
demolition of the pilot plant at Tap Shek Kok was approved by
EPD on 23 June 2009.
The EP for the demolition project was issued by EPD on 24 June
2009.
Both the approved EIA report and EP issued is placed on the EIA
Ordinance Website (http://www.epd.gov.hk/eia).
- Current Status of the Pilot
Plant
Subsequent to the approval of the EIA report and issue of the
EP, preliminary activities for the decommissioning of the pilot
plant were started.
Tenders were called for the demolition works from potential
contractors on the list of Registered Specialist Contractors
(Demolition Works) maintained by the BD. The tender was awarded
on 24 July 2009.
The demolition procedure as prescribed by the BD was followed
with submission of a Site Supervision Plan with supporting
documents followed by an application on 11 August 2009 for consent to the carrying
out of the demolition works .
Precautionary measures as required by the BD including erection
of hoarding and barriers on the demolition site were carried
out.
Consent to the commencement and carrying out of the works was
given by the BD on 8 September 2009.
The decommissioning of the pilot plant commenced on 15 September
2009 and the demolition works were conducted
in compliance with regulatory guidelines and the terms and
conditions including the mitigation measures prescribed in the
EIA Report and EP.
Practical completion of the demolition works was reached on 7
December 2009 according to schedule.
|