Monitoring of The Eco-co-combustion Pilot Plant
Introduction
Click picture
below to view charts
During
operation of
the
Eco-co-combustion Pilot Plant, on-site exhaust gas emission and off-site air
quality was closely monitored. The
Hong Kong Productivity Council has been commissioned to be the Independent
Consultant on the project ("the Independent Consultant"), which had appointed
the
Hong Kong Baptist University to perform the sample analysis.
Two off-site stations were established in the Tuen Mun district located in Butterfly
Estate and Lung Kwu Tan Village for baseline monitoring of ambient air quality.
The parameters to be monitored include
total suspended particulates (TSP),
respirable suspended particulates (RSP),
nitrogen dioxide (NO2),
sulphur dioxide (SO2),
dioxins
and heavy metals.
The operation of these two monitoring stations was
started in
December 2004 and continued to operate until one
month after the pilot plant was shutdown.
Emisssion monitoring equipment
was also installed
in the chimney of the pilot plant
for the continuous monitoring of the exhaust gas emission. Total organic carbon (TOC),
hydrogen chloride (HCl), hydrogen fluoride (HF), sulphur dioxide (SO2),
nitrogen oxides (NOx), carbon monoxide (CO) and opacity
were closely
monitored.
For dioxins
and heavy metals, measurements were collected on a periodic basis (please refer
to the sampling frequency in the later part of this web page) by the
Independent Consultant. All results for on-site continuous emission
(normal operation) were
published on this web page within three working days while the monitoring results
for off-site periodic measurement were published within three working days upon receipt of
verified reports
from the Independent Consultant.
Monitoring
Results
(1)
Off-site monitoring included the measurement of total suspended particulates (TSP), respirable
suspended particulates (RSP), nitrogen dioxide
(NO2), sulphur dioxide
(SO2),
dioxins and heavy metals. This data was provided by the Independent Consultant on
a monthly basis.
|
(2)
On-site continuous emission
monitoring (CEM) includes the measurement of total organic carbon (TOC),
hydrogen chloride (HCl), hydrogen fluoride (HF), sulphur dioxide
(SO2),
nitrogen oxides
(NOx),
carbon monoxide (CO) and opacity. This data was collected by the devices
installed in the chimney.
(3)
On-site periodic monitoring includes the measurement of dioxins and heavy metals. This data
was
provided by the Independent Consultant.
Sampling
frequency for the off-site monitoring parameters:
NO2
and SO2 |
Continuous basis |
TSP and RSP |
Once every 6
days |
Heavy metals |
Sample taken
once every 6 days and analyzed by composite digestion once a month |
Dioxins |
Twice a
month |
Approval
from EPD
Subsequent to the successful load commissioning trials, the
Environmental Protection Department has agreed to the use of the
pilot plant for a limited period during which the company
analysed recovery and recycling as well as the disposal of
non-recyclable materials. The operating scale, including both
duration and volume of waste being handled remained the same
as originally planned.
Renewal of License
As the original Specified Process (SP) license expired before
the completion of the pilot projects, an application for renewal
of the license was submitted to the
Environmental Protection Department so as to complete the plant
testing of the technology. There was no increase in either
the 16-week cumulative operating time of the pilot plant or the volume of
waste being handled (not more than 24 tonnes per day).
Note: The SP license was renewed effective from 25th
November 2005 and expired on the 24th November 2007
under the same terms and conditions of operation as before. As
the project is completed, there will be no further renewal.
Status of Pilot Plant Operation
The pilot
plant project has completed its research objective and the pilot
plant operation was closed down on 17th December 2005.
Decommissioning of the Pilot Plant
The decommissioning of the pilot plant is a Designated Project
(DP) as it is included in the category of projects which
requires an Environmental Permit (EP) for decommissioning under
the Environmental Impact Assessment Ordinance (EIAO Cap.499).
The decommissioning process for the pilot plant was started with
the preparation and submission of a Project Profile (PP) to the
Environmental Protection Department (EPD) in accordance with the
guidelines under the EIAO. Following review and public
consultation on the PP, the EPD has issued an Environmental
Impact Assessment Study Brief (EIA-SB). An EIA report conforming
to the requirements of the EIA-SB was prepared for submission to
EPD to obtain an EP for decommissioning of the pilot plant.
As part of the EP application process, a Contamination
Assessment Plan (CAP) has to be approved by the EPD.
Accordingly, a CAP was prepared and submitted to EPD for review
and comments. The CAP was approved by the EPD on 29 January 2008
and Site Investigation (SI) work was carried out in compliance
with the regulatory requirements.
After completion of the SI work, a Contamination Assessment
Report (CAR) was compiled and presented to EPD and approval was
received on 27 May 2008.
A demolition permit from the Buildings Department (BD) is also
required for the decommissioning of the pilot plant. A
Demolition Plan was prepared in co-operation with the building
consultant and an application for approval of the Demolition
Plan was submitted to the BD on 20 January 2009. The Demolition
Plan was approved by the BD on 13 March 2009.
Work was continued on the EIA in co-operation with the
environmental consultant and after a series of studies and
evaluation the EIA report was submitted to the EPD on 20 March
2009. Following further amendments as required by the EPD and
consultation, advice was received from the EPD on 4 May 2009
that the EIA report is suitable for public inspection. The EIA
report was made available for public inspection from 15 May 2009
to 13 June 2009.
After the public inspection period, the EIA report for the
demolition of the pilot plant at Tap Shek Kok was approved by
EPD on 23 June 2009.
The EP for the demolition project was issued by EPD on 24 June
2009.
Both the approved EIA report and EP issued is placed on the EIA
Ordinance Website (http://www.epd.gov.hk/eia).
Current Status of the Pilot Plant
Subsequent to the approval of the EIA report and issue of the
EP, preliminary activities for the decommissioning of the pilot
plant were started.
Tenders were called for the demolition works from potential
contractors on the list of Registered Specialist Contractors
(Demolition Works) maintained by the BD. The tender was awarded
on 24 July 2009.
The demolition procedure as prescribed by the BD was followed
with submission of a Site Supervision Plan with supporting
documents followed by an application on 11 August 2009 for consent to the carrying
out of the demolition works.
Precautionary measures as required by the BD including erection
of hoarding and barriers on the demolition site were carried
out.
Consent to the commencement and carrying out of the works was
given by the BD on 8 September 2009.
The decommissioning of the pilot plant commenced on 15 September
2009 and the demolition works were conducted
in compliance with regulatory guidelines and the terms and
conditions including the mitigation measures prescribed in the
EIA Report and EP.
Practical completion of the demolition works was reached on 7
December 2009 according to schedule.
Contacts
For any enquiries on the project or the monitoring reports, please contact:
Mr. Michael Wong
Telephone No: (852) 2440 5209
Fax No: (852) 2441 3421
Email:
michaelw@gich.com.hk
|